https://www.econologie.info/share/partag ... hfShqs.doc
Manufacturing dossier for a biomass boiler
This boiler is based on the work of Jean Pain, who discovered that a pile of decaying plant waste of several m3 emits a temperature of up to 75 ° for several months, so it was heated.
This boiler does not emit co2 because it does not consume any material, it recovers the heat from the decomposition of plants.
Manufacturing:
the ideal would be stainless steel but expensive and difficult to weld (we can also recover a tank from an old stainless steel heating flask), failing that we will be satisfied with heating quality steel, welded with arc, protected against corrosion by treatment.
To get started, get:
a tube diameter 300 long 1,5m (found in scrap yards)
two domed bottoms diam 300
two tubes 26x34 long 50cm
two small pieces of 15x21 and 20x27
iron U (thick) four pieces of 50cm
two welding flanges 26x34 DN 50
bend the U-irons at 90 ° to about 35cm (heat them red with a blowtorch) to make the feet
pierce the domed bottoms in their center (one at 15, the other at 20)
weld the domed bottom drilled at 15 at one end of the 300 tube (top of the boiler)
make a turbulator * (it must slow down the circulation of water in the boiler), slide it into the tube of 300 and weld the other convex bottom weld a piece of threaded tube (15x21 on the side drilled at 15 for the purge) and (20x27 side drilled at 20 for emptying)
weld the feet along the bottom of the boiler (make sure to weld ALL sides)
pierce the body of the boiler about 10cm from the upper edge at 26, point a 26x34 tube at the square and point the flange to be welded (check the squareness) do the same at 10cm from the lower edge (return pipe) and weld the whole
put the boiler vertically, it must stand upright very stable
place perforated plates with gaskets on the flanges, valves on the drain and purge, inflate with air (at least 4 bars) and test the welds using a product for gas leaks
in the event of a leak, repeat the welds (grind and resume) otherwise fill it with water, have a plumbing pump lend a test pump and pressurize water at 20 bars for 4 hours.
Put a good coat of anti-rust paint on the entire boiler (also the feet), let dry at least a week before applying an epoxy paint
Put the boiler in place and connect to the heating circuit with isolation valves (be careful to put a 3 bar valve upstream)
the boiler must be kept straight during loading (fix it on the ground or against a wall with a minimum distance of 50cm from the wall), cover with 3m3 of fine ground vegetable waste (wood, brush, brambles) sprinkle with 5 buckets of rain water, leave for three days, then cover with 10cm of soil.
The reaction begins between 15 to 20 days and lasts more than 8 weeks, after which the temperature decreases, when it is no more than 30 ° we can remove the mixture that has composted and use it as or mixed with Earth .
Each year check the condition of the anti-rust treatment, carefully brush and redo the paints.
NOTE: several boilers can be put in a battery and run in turn. In this case, the waste must be stored in a dry place or produced as and when using a shredder.