This government agency has striven to make plausible the production of electricity in France mainly from wind (63%) and photovoltaic (17%).
In summary, according to ADEME, France could do without fossil fuels, and at the same time nuclear, with eight "ifs":
1) If the annual electricity consumption decreased to 422 terawatt hours (TWh1) in 2050 (from 470 TWh in 2016), with a population increased by 10% and new electrical uses (electric transport, heating by pump at heat,…).
2) If the demand for electricity could be largely driven downward (postponement, erasure,…) in the absence of wind and / or sun and by counting on imports, or else, on the contrary, “stimulated” on order consume a lot during peak production, when there is sun and wind.
3) If the losses after storage and destocking of surpluses were low.
There are only 45 TWh of losses expected when they will be approximately triple (130 TWh), in particular because of the poor methanation yield.
However, the transformation of electricity into methane (for storage), then again into electricity in a gas power plant (called power to power), is the main means of storage / destocking of electricity chosen by the ADEME which fixed its yield at 33%.
In reality, it is less than 15% (transport of this electricity to electrolysers (efficiency 97%), production of hydrogen (70%), compression (80%), separation and compression of CO2 (60%) and methanation reaction (70%).
Finally, it is necessary to transform this methane in a gas power plant (60% maximum).
As a result, the final yield is less than 15% (13,7%).
In addition, no major achievement exists in this area, and there are always additional losses in reality ...
To recover the 19 TWh envisaged by ADEME, it would therefore be necessary to inject at least 125 TWh, and agree to “lose” (and therefore pay at a loss) more than 100 TWh of electricity each year…
4) If large-scale electricity storage for several weeks existed. This is not the case. Dams (10% of production in France) are not or only slightly expandable. The massive, efficient and economical storage process remains to be invented.
The report predicts that the Pumping Energy Transfer Stations (STEP) will restore a power of 7 gigawatts (GW) for 32 hours straight.
However, currently, only 2 GW can be returned during this time (Grand'Maison and Montézic), and only 5 GW for a maximum of 5 hours…
The maximum storage capacity available today is only 4 GW and the storable energy capacity is only 0,1 TWh.
In comparison, the need for power in France varies from 30 GW to 90 GW and daily consumption varies around 1,3 TWh per day (more in winter, less in summer).
5) If we knew where to install these storage means.
Will we have to build new dams and drown valleys, or dig thousands of lakes on our cliffs along the coasts?
Where will be the suitable sites (for example caves) to store energy by compressing air (second means of storage planned)? This report plans to restore 13 GW of power and 13 TWh of electricity annually.
6) If we knew where to find concentrated CO2 "free" near the methanation plants because the cost of CO2 is not taken into account in the study.
7) If the costs of storage were not outrageously minimized by being at least halved.
They do not take into account investments in electrolysers, which are planned to install a power of 17 GW to supply the hydrogen necessary for the production of methane.
The cost projections for short-term storage are assimilated to the air compression sector (CAES: Compressed Air Energy Storage) whose overall efficiency is 50% and not 81% as this report indicates.
It would therefore be necessary to inject at least 26 TWh to recover the 13 TWh planned.
If batteries (mentioned in the report) are used, then… neither the cost of using this very expensive means, nor the huge quantities of batteries (more than 10 tonnes?) To absorb or restore 000 GW are discussed. power.
Finally, and above all, it would take up to 6 kWh of electricity at 12 c € / kWh (without taxes according to ADEME) to find, after destocking, a kWh ... very expensive. You will have to agree to multiply the price by 6 (more than 72 c € / kWh), without taking into account the depreciation of the installations…
The selling price for the production of electricity on the market is today around 4 c € / kWh… and 15 c € / kWh for individuals with taxes and home transport.
If, if, if ... The song of "if" reigns to supply France with a high proportion of intermittent and fatal renewable energies such as wind turbines and photovoltaic panels. And it is well known that with "if" we would bottle Paris.
But if the French want to mortgage their future and that of their children by making all these senseless bets, they are free to be charmed by the fatal song of if ... (reins) from ADEME. But our politicians would be well advised not to believe blissfully that everything will be resolved as if by magic in the best of all worlds by succumbing to the songs of "ifs".